Historic Mitchelville Freedom Park is getting two new driveways because it is getting a building. Since early August 2026, Town crews have worked from 7 a.m. to 5 p.m. daily on a project that adds two entrances and exits on Beach City Road, a paved loop road, 36 permeable parking spaces, drainage and permanent signs. Everything is scheduled to be finished by the week of December 21, 2026. The Town's project page says the improvements "will support the new Mitchelville Freedom Park Archaeological Research Facility and Auditorium."
Nearby, Fish Haul Beach Park is going through its own rebuild, at a slower pace. For anyone who lives near the north end of Hilton Head, these two parks are the closest public open space, and both are being made more permanent this winter. Mitchelville is becoming a place where archaeology is done on site. Fish Haul's new sand is getting dunes to hold it in place.
The road at Mitchelville is sized for the building
Most of what visitors have seen at Mitchelville so far is outdoor. The park's official site describes its Praise House and Bateau exhibits, and private guided tours are available by reservation. The loop road and 36 new parking spaces are there to serve a building with a lab and an auditorium.
That building broke ground on August 27, 2025, at 40 Harriet Tubman Way. The Hilton Head Sun reported that it would hold an archaeology lab, research space, an auditorium and educational displays. In July 2026, WTOC reported that it is the first permanent building on the campus, that the Mellon Foundation is paying for it, and that the auditorium will seat about 84 people for programs. The station said Executive Director Ahmad Ward expected the building to open later in the fall.
"It's a big deal for us to have this building on our site," Ward told WTOC.
The Town puts the access and parking work at $2,310,200, paid for with State Accommodations Tax funds, with MAJ listed as contractor. That money covers the road and parking. It is a separate figure from the cost of the building.
Why a lab on the island changes what the park can tell you
In the same report, WTOC explained what the building is for. Archaeologists working at Mitchelville will be able to process their finds on site rather than sending material to outside labs.
The digging near the construction zone shows why that matters. WTOC reported that archaeology confirmed a historic church once stood there. The praise house replica placed on the site in 2014 had been built, without anyone knowing, right over the church's footprint. Digging further in the same spot turned up an Indigenous imprint about 4,000 years old, which researchers connect to the Escamacu and Kusabo First Nations, according to Ward. The park is also adding a church frontage exhibit nearby.
So a field where finds were packed up and shipped away is becoming a site where they get studied, and then presented in an 84-seat room a short walk away. The new entrances and loop road are what make that room usable.
The park stays open while the work goes on, and the Town asks visitors to follow traffic control and posted construction signs. That matters most in December. Last year the park held its Holiday Nights & Lights drive-through from December 6 to 8, 2025, the event's sixth year, with a theme of "The Gullah Village." Any drive-through event this season would run on a site that is still finishing its new road. The park's holiday page is the place to check for this year's details.
Fish Haul is being anchored on a slower clock
Fish Haul's work comes from the island-wide renourishment that finished in July 2026. That project restored about 9.2 miles of beach with 2.4 million cubic yards of sand. In an October 5 release, the Town said waves, tides and storms keep moving sand after a renourishment. Its fix is to stabilize certain dune areas with sand fencing and plants.
The Fish Haul Beach Park shoreline is one of six areas on that list. The other five are Tower Beach Club to Seaside Sparrow Road, Coligny to Shipyard, part of Palmetto Dunes, Singleton Beach, and Burkes Beach to Bradley Beach. Fish Haul faces Port Royal Sound rather than the ocean, which makes it the odd one out.
Here is how the work is designed, according to the Town:
- Fencing about four feet tall, made of untreated wood slats
- Sections set at angles to catch sand, with gaps left open around them
- Dune plants added along new fencing where needed, starting on the beach side and running about 20 feet back toward the dunes
The fencing was scheduled for October 5 through the end of October. Dune planting is expected to start in early December and finish in spring 2027. Mitchelville's road is due to be done before Christmas. Fish Haul's dunes will still be growing in through the spring.
The north-end schedule, side by side
Laid out together, the two parks overlap most in December. A couple of nearby Town projects run on the same calendar.
| Project | Location | Scheduled window |
|---|---|---|
| Mitchelville entrances, loop road and parking | Beach City Road at Historic Mitchelville Freedom Park | Early August 2026 to the week of Dec. 21, 2026 |
| Archaeological Research Facility and Auditorium | 40 Harriet Tubman Way | Broke ground Aug. 27, 2025; WTOC reported a fall 2026 opening expected |
| Sand fencing | Fish Haul Beach Park shoreline | Oct. 5 to end of October 2026 |
| Dune planting | Fish Haul Beach Park shoreline | Early December 2026 to spring 2027 |
| North End Post Office Phase 2 | Gum Tree Road and Marsh Point Road rear entrance closed | Through Nov. 15, 2026 |
The post office project is the closest to finishing. The Town's August update said Phase 2 would run through November 15. During the work, drivers use the William Hilton Parkway entrance while the rear entrance off Gum Tree Road and Marsh Point Road stays closed, and the post office remains open. The project adds a 10-foot-wide path meant to link Northpoint, Gum Tree Road and the public schools campus.
On Dillon Road, the Town announced in July that St. James Baptist Church and the Cherry Hill School will move to a 4.67-acre campus on Union Cemetery Road. The plan includes a church of about 11,975 square feet with a 250-seat sanctuary, a 120-seat fellowship hall, and the relocated school building. The Town expected construction to begin in fall 2026, depending on Planning Commission review, zoning actions and public hearings. Details are in the Town's announcement.
Using Fish Haul between the seasons
The Town's October release says current beach access routes stay open during the fencing work. The Town's park page lists Fish Haul at 124 Mitchelville Road, describes it as overlooking Port Royal Sound and good for walking, birdwatching and resting, and notes restrooms and parking. Amenities also include beach access and a beach wheelchair.
The Town's parking page has the details:
- Beach parks are open daily from 6 a.m. to 10 p.m.
- Fish Haul has 93 paid spaces and four ADA spaces.
- The Barker Field Expansion lot adds 70 free overflow spaces and two ADA spaces.
- Residents with a Town beach parking permit park free at Town beach parks.
- Peak-season visitor rates of $3 an hour on weekdays and $5 on weekends apply from March 1 through September 7, enforced from 7 a.m. to 5 p.m.
The sand fencing was scheduled for October and dune planting for early December, so both fall after the September 7 end of peak season. Hilton Head Audubon scheduled a fall shorebird walk and wildlife beach area tour at Fish Haul for October 7. For anyone birding the Sound-side beach this winter, the planting along the fencing is scheduled to continue into spring 2027.
When friends ask what's new up by Mitchelville and Fish Haul, or when you're planning a winter on the north end of the island, we're glad to talk it over. Schedule a Free Concierge Consultation with Tisha & Co Realtors. We've lived on this side of the bridge since 1996.